Issue No. : 1
Issue Date : February 2010
Project No. : 768
Joint User Complex and
Wholesale Fish Market at Area 44, Tuen Mun
Sixth Quarterly Environmental Monitoring & Audit Report
(November 2009 ¡V January
2010)
Prepared By:
Allied
Environmental Consultants Ltd.
COMMERCIAL-IN-CONFIDENCE
Issue
No. : 1
Issue Date : February 2010
Project No. : 768
Joint User Complex and Wholesale Fish Market at Area
44, Tuen Mun
Sixth Quarterly Environmental Monitoring & Audit Report
(November 2009 ¡V January
2010)
Prepared
By:
Allied Environmental Consultants Ltd.
COMMERCIAL-IN-CONFIDENCE
Author:
Nic Lam
BSc(Hons)
Checked: Approved:
Adi Lee Grace Kwok
BEng(Hons)
MEng MHKIEIA BEng(Hons) MHKIEIA
MHKIOA
MISWA MIAIA MRAPA LEED AP
This report has been prepared by Allied Environmental Consultants Limited
with all reasonable skill, care and diligence within the terms of the Agreement
with the client, incorporating our General Terms and Conditions of Business and
taking account of the resources devoted to it by agreement with the client.
We disclaim any responsibility to the client and others in respect of any
matters outside the scope of the above.
This report is confidential to the client and we accept no responsibility
of whatsoever nature to third parties to whom this report, or any part thereof,
is made known. Any such party
relies upon the report at their own risk.
Table of Contents i
List of Tables ii
List of Figures ii
List of Appendices ii
EXECUTIVE SUMMARY 1
1. PROJECT BACKGROUND 2
1.1 Project Organization and Contact Personnel 2
2. SENSITIVE RECEIVERS 3
3. SUMMARY OF EM&A
REQUIREMENT 3
4. MONITORING METHODOLOGY 5
4.1 Monitoring Programme 5
4.2 Air Quality Monitoring 5
4.3 Noise Monitoring 5
5. RESULTS 6
5.1. Air Quality 6
5.2. Noise 6
5.3. Weather Conditions 6
6. SITE INSPECTION
& AUDIT 7
7. Non-compliance,
Complaints, Notifications of Summons and Successful Prosecutions 8
8. OTHERS 8
9. RECOMMENDATIONS AND CONCLUSIONS 8
9.1. Recommendations 8
9.2. Conclusions 9
Table 1 Contact Details of
Key Personnel
Table 2 Action and Limit Level for Air Quality Impact
Monitoring at Yuet Wu Villa
Table 3 Action
and Limit Levels for Construction Noise Impact Monitoring
Table 4 Event
Action Plan
Table 5 Noise Monitoring Equipment
Table 6 Summary of Weather Conditions during the
Monitoring Period
Table 7 Summary
of Site Inspections
Figure
1 Site
Location Plan
Figure
2 Location
of Air Quality Monitoring Station
Figure
3 Location
of Noise Monitoring Station
Figure
4 Photos
of Air Quality Monitoring Station
Figure
5 Photos
of Noise Monitoring Station
Figure 6 Photos
of Construction Site for Junior Police
Officers' Married Quarters
Appendix A Detail
Schedule of Monitoring Programme
Appendix B Calibration
Record of High-Volume TSP Sampler
Appendix
C Calibration
Certification of the Sound Level Meter and Calibrator
Appendix
D Summary of 1-Hour TSP Monitoring
Record
Appendix
E Summary of 24-Hour TSP Monitoring
Record
Appendix
F Summary of Noise Monitoring Record
Appendix
G Wind Record from Hong Kong Observatory
Appendix
H Mitigation Measures Implementation Schedule
for Construction Stage
Allied Environmental Consultants Limited (AEC) has been
appointed to conduct an environmental monitoring and audit (EM&A) program for the proposed Joint User Complex and Wholesale Fish Market at Area 44,
Tuen Mun. The construction works was commenced on
Based on the monitoring results, the air
quality and construction noise level complied with the environmental
requirements in EM&A Manual. There were no environmental complaints
received in this quarter. No notification
of summons or prosecution was received.
Construction activities undertaken from November 2009 to January 2010 included construction of superstructure from M/F to 1/F, 1/F to 2/F and 2/F to R/F, installation of E&M services
concealed conduit to slab of superstructure, construction
of underground E&M services, wall rendering at G/F and M/F, erection of
block wall at G/F, 1st fixing of E&M ceiling services, erection
of bamboo scaffolding, installation of concealed E&M service pipe to
superstructure, installation of metal truss at roof, last manhole construction
and connection works. Potential environmental impacts include
dust generation from stockpiles of dusty materials, the superstructure, walls and building services; noise
from operation of the equipments; runoff from building services and the storage
of various C&D and chemical wastes. The Contractor should properly
implement the required environmental mitigation measures as per the
implementation schedule in the EM&A manual to ensure no significant adverse
environmental impacts to be arisen from the construction works. The Contractor
was reminded to maintain good housekeeping throughout the construction phase.
A Joint User
Complex and Wholesale Fish Market (WFM Complex) at Area
The subject site is located at Castle Peak
Bay of Tuen Mun given in Figure 1. The subject site is bounded to the north by a future local
open space presently used as a temporary car park, to the east by
Key personnel and contact particulars are summarized in Table 1.
Table 1 Contact
Details of Key Personnel
Role |
Department / Company |
Names |
Contact Number |
Fax Number |
Lead User
Department |
Agriculture,
Fisheries, and Conservation Department |
Mr. K.H. Chan Ms. Louise Li |
2150 7092 2150 7104 |
2314 2866 |
Environmental
Permit Holder |
Architecture
Services Department |
Mr. S.W. Chow Ms. Susana Chan |
2867 3716 2867 3706 |
2523 9622 |
Architect |
P&T
Architects and Engineers Ltd. |
Ms. Sarah Ng Ms. Vivian Law |
2835 3548 2832 3046 |
2891 3834 |
Main
Contractor |
W. Hing
Construction Co. Ltd. |
Mr. Andy Chan Mr. Jim Lee |
9630 7404 6105
4076 |
8343 9188 |
Environmental
Team Leader |
Allied
Environmental Consultants Ltd. |
Ms. Grace
Kwok |
2815 7028 |
2815 5399 |
Independent
Environmental Checker |
Cinotech
Consultants Ltd. |
Dr. Priscilla Choy |
2151 2089 |
3107 1388 |
Air Sensitive Receivers (ASRs) within
Noise Sensitive Receivers (NSRs) within
For regular
impact monitoring, the sampling frequency of at least once in every six-days,
shall be strictly observed at the monitoring station for 24-hr TSP
monitoring. For 1-hr TSP
monitoring, the sampling frequency of at least three times in every six-days should
be undertaken when the highest dust impact occurs. For noise monitoring, one
set of measurement between 0700-1900 hours on normal weekdays. Leq(30 min) shall be used
as the monitoring parameter.
From baseline monitoring results, the proposed Action and Limit Levels for air quality are summarized in Table 2. The
average baseline 1-hr TSP value of 129£gg/m3 and
24-hr TSP value of 65£gg/m3
measured at Block 15, Yuet Wu Villa was used to determine the action and limit
level for air quality impact monitoring. The proposed Action and Limit Levels
for construction noise are summarized in Table 3.
Table 2 Action
and Limit Level for Air Quality Impact Monitoring at Yuet Wu Villa
Parameters |
Baseline Level (£gg/m3) |
Action Level (£gg/m3) |
Limit Level (£gg/m3) |
24 Hour TSP Level |
65 |
173 |
260 |
1 Hour TSP Level |
129 |
334 |
500 |
Table 3
Action and Limit Levels for Construction Noise Impact Monitoring
Time Period |
Action Level |
Limit Level |
Daytime (0700-1900 hours) on weekdays |
When one documented compliant is received |
Dwelling 75dB(A)1 School 70dB(A)1 (65dB(A) during
examinations)1 |
1900-2300 on any day and 0700-2300 on
Sunday and general holidays, for use of PME2 |
When one documented compliant is received |
65dB(A)3 |
All days during the night-time (2300-0700
hours) 2 |
When one documented compliant is received |
50dB(A)3 |
Note: 1. Construction
noise criteria stipulated in the TM-EIAO
2. A Construction
Noise Permit (CNP) shall be required for the carrying out of the construction
work during the restricted hours (1900-2300 on any day
and 0700-2300 on Sunday and general holidays, for use of PME; and All days
during the night-time (2300-0700 hours))
3. Area sensitivity rating of the monitoring location
is ¡§B¡¨.
Should non-compliance of the above Action and Limit levels occurs, the
contractor shall undertake corresponding action in accordance with
the proposed Event Action Plan given in EM&A Manual. A summarized general
Event Action Plan is given in Table 4. Details should be referred to the Event Action Plan in the
EM&A Manual.
Level |
Step
1 |
Step
2 |
Step
3 |
Action |
l Identify source l Check monitoring data and working methods |
l Contact project manager to discuss and
implement remedial action l Rectify any unacceptable practice l Amend working methods if appropriate l If exceedance continues, commence
additional monitoring |
l Notify client/project manager following
correct of the situation l Cease additional monitoring if exceedance
stops |
Limit |
l Identify source l Notify client/project manager l Check monitoring data and working methods l Repeat measurement to confirm finding l Commence additional monitoring |
l Take immediate action to avoid further
exceedance l Submit proposal for remedial actions to
client/project manager within 3 working days l Implement the agreed proposal l If exceedance continues, amend and
resubmit the proposal |
l Notify client/project manager following
correction of the situation l Cease additional monitoring if exceedance
stops |
Air quality monitoring and noise
monitoring were conducted at Block 15, Yuet Wu Villa on
2nd, 7th, 13th, 19th and 25th
November 2009, 1st, 7th, 12th, 18th,
24th and 30th December 2009 and 5th, 11th,
16th, 22nd and 28th January 2010. Appendix A displayed the
detail schedule of the monitoring programme. Air
quality monitoring station was set up at the roof top of the residential block
and noise monitoring was conducted at
A
construction site for the proposed Junior Police Officers' Married Quarters is
located at
1-hour and 24-hour TSP air quality monitoring was conducted at the
designated air quality monitoring location using a High Volume TSP Sampler (Model No: Anderson
GMWS-2310 ACCU-VOL) at the designated location. The Calibration
Record of the High-Volume TSP Sampler is given in Appendix B. 24-hour TSP samples were taken every six
days. 1-hour TSP samples were taken three times a day
between 0700-1900 hours.
Noise monitoring was conducted
at the designated noise monitoring location between 0700-1900 hours using a sound
level meter which complies with the International Electrotechnical Commission
Publications 651:1979 (Type 1) and 804:1985 (Type 1). Noise instrumentation
details are given in Table 5 and the Calibration Certificate for the sound level meter
and calibrator is given in Appendix C.
Table 5 Noise
Monitoring Equipment
Manufacturer |
Type/Model No. |
Equipment |
RION |
Model NL 31 |
Precision Sound Level Analyzer with windshield |
RION |
|
Calibrator |
Noise levels measurements
were recorded in terms of thirty minutes A-weighted equivalent continuous sound
pressure level (Leq(30min)) on a
weekly basis. The sound level meter was calibrated immediately prior to and
following each noise measurement. The meter was mounted on a tripod at a height
of
Noise measurements were not made in the presence of fog, rain, and wind
with a steady speed exceeding
No exceedance was recorded in this quarter. Summary and graphical plots of
air quality monitoring record of 1-hour TSP levels and 24-hour TSP levels are
provided in Appendices D and E. The weighing of the filter paper used in the monitoring
will be undertaken by ALS Laboratory Group Environmental Division. (HOKLAS
Registration No.: 066)
Noise monitoring results in terms of Leq(30min),
L10(30min) L90(30min) were measured at the designated
noise monitoring location. L10 and L90 represent sound
levels that are exceeded 10% and 90% of the time respectively. Normally, L10
measurements can be considered as the average peak levels, whilst L90
levels can be considered as the average background noise levels.
No exceedance was recorded in this quarter. Summary of noise monitoring record is
provided in Appendix F.
Weather data of the monitoring station were obtained from the nearest
Hong Kong Observatory (HKO) Tuen Mun automatic weather station located at Tuen
Mun Town Park (63 mPD).Table 6 summarizes the wind data during the monitoring
dates. Wind record from HKO is shown in Appendix G.
Table 6 Summary
of Weather Conditions during the Monitoring Period
Date |
Weather |
Prevailing Wind Direction |
Daily Average Wind Speed (m/s) |
2
November 2009 |
Sunny |
NE |
4.92 |
7 November 2009 |
Cloudy |
S |
2.19 |
13 November 2009 |
Cloudy |
N |
3.28 |
19 November 2009 |
Sunny |
N |
2.90 |
25 November 2009 |
Sunny |
S |
1.18 |
1
December 2009 |
Sunny |
N |
2.09 |
7 December 2009 |
Cloudy |
N |
1.50 |
12 December 2009 |
Sunny |
S |
2.51 |
18 December 2009 |
Cloudy |
NE |
3.76 |
24 December 2009 |
Sunny |
N |
1.15 |
30
December 2009 |
Cloudy |
NE |
1.35 |
5 January 2010 |
Cloudy |
SE |
2.73 |
11 January 2010 |
Cloudy |
N |
2.14 |
16 January 2010 |
Sunny |
N |
0.86 |
22 January 2010 |
Cloudy |
NE |
1.57 |
28 January 2010 |
Cloudy |
N |
0.02 |
Weekly site
inspections were carried out by representatives of the ET. Thirteen site
inspections were conducted on 6th,
13th, 20th and 29th November 2009, 4th,
11th, 18th, 24th and 30th December
2009, 8th, 15th, 22nd and 29th January
2010.
Key findings are summarized in Table 7.
The mitigation
measures undertaken by the Contractor are effective in minimizing the
environmental impact; however, the Contractor should implement these mitigation
measures more effectively in order to prevent causing any adverse environmental
impact.
Table 7 Summary
of Site Inspections
Date |
Observations |
Action taken by contractor |
Outcome |
6 November 2009 |
Haul road
appeared dry and dusty. |
Contractor was requested to increase the frequency of
watering. |
The situation
was rectified immediately. |
13 November 2009 |
No observations during inspection. |
Contractor was required to keep up with the mitigation
measures. |
|
20 November
2009 |
No observations during inspection. |
Contractor was required to keep up with the mitigation
measures. |
|
19 November
2009 |
No observations during inspection. |
Contractor was required to keep up with the mitigation
measures. |
|
4 December 2009 |
No observations during inspection. |
Contractor was required to keep up with the mitigation
measures. |
|
11 December 2009 |
No observations during inspection. |
Contractor was required to keep up with the mitigation
measures. |
|
18 December 2009 |
No observations during inspection. |
Contractor was required to keep up with the mitigation
measures. |
|
24 December
2009 |
No observations during inspection. |
Contractor was required to keep up with the mitigation
measures. |
|
30 December
2009 |
No observations during inspection. |
Contractor was required to keep up with the mitigation
measures. |
|
8 January 2010 |
No observations during inspection. |
Contractor was required to keep up with the mitigation
measures. |
|
15 January
2010 |
No observations during inspection. |
Contractor was required to keep up with the mitigation
measures. |
|
22 January
2010 |
Haul road
appeared dry and dusty. |
Contractor was requested to increase the frequency of
watering. |
The situation
was rectified immediately. |
29 January
2010 |
No observations during inspection. |
Contractor was required to keep up with the mitigation
measures. |
|
During site inspections in this quarter, no non-conformance of implementation of environmental
mitigation measures was identified. All environmental mitigation measures for construction stages stated in
the
approved EIA Report, EM&A
Manual and Environmental Permit shall be carried out throughout the whole
construction period as shown in Appendix H.
In this quarter, no complaints, inspection notices, and notifications of summons or prosecution were
received.
696.75 tonnes of inert
C&D material was disposed at public fill. 154.71 tonnes of waste including
general refuse and non-inert C&D waste such as timber and bamboo were
disposed to landfill. No chemical waste was transported off site in this quarter.
In accordance with the environmental site
audits undertaken during the reporting quarter, the following recommendations are made:
¡P
Increase the frequency of watering when the haul road
appeared dry.
The ET will keep
track on the EM&A programme to ensure compliance of
environmental requirements and proper implementation of all necessary
mitigation measures.
Environmental monitoring
has been carried out for the proposed Joint User Complex and Wholesale Fish Market at Area 44, Tuen Mun. 1-hour and 24-hour TSP air quality monitoring and noise monitoring was
conducted at Block 15, Yuet Wu Villa during the period from 1st November 2009 to 31st January
2010, in accordance with EM&A Manual and the
requirement under Environmental Permit (No. EP-296/2007).
All monitoring results were checked and reviewed. 48 sets of 1-hour
TSP level monitoring, 16 sets of 24-hour TSP level monitoring, and 16
sets of noise monitoring were carried out during the reporting quarter. No exceedance of any of the monitoring data was recorded. No environmental complaints and notification of summons
or prosecution were received during the second
quarter.